scope:
15 onsite parking Stalls and sidewalks/paths to meet ADA requirements
Grading of site to allow for stormwater drainage and balance cut/fill
Design of driveway, parking, and semi-truck loading ramp
Design of stormwater collection system from roof downspouts, as well as catch basins in the driveway or any low points around the building
Design underground tanks, packaged pumping system, and piping to supply the new building with potable water
Design winery wastewater process for max capacity of 50,000 cases
Add septic tank to be pumped to septic leach/drain field separate from wastewater
Driveway Access and ROW permit applications